MARSEILLES DAM REPAIRS

Marseilles, Illinois

The Corps of Engineers awarded Massman Construction Co. a contract to perform repairs to the Marseilles Dam in Marseilles, Illinois. The dam was damaged by several runaway barges that collided with the dam as a result of strong river currents from heavy rainfall. Massman completely replaced three tainter gates and repaired two others.

Erection of the shoring system to support Gates 2 and 3 during the replacement of the trunnion girder began once the riprap was removed. All material had to be picked from the barge located upstream of the dam using the Manitowoc 4100 and moved over the dam to be set in place on the downstream side. Crews accessed the shoring installation from two Snorkel man-lifts located downstream on the existing rock dike.

The shoring system, consisting of six (three per gate) HP 12 x 53 shoring piles tied back to the concrete piers, was installed and the gates were lowered onto the shoring. Two platforms were then erected off the shoring piles on either side of Pier 2 and the drill platform was erected on the downstream face of Pier 2.

The crew successfully removed the trunnion pins at Pier 2 from Gates 2 and 3 to release all load from the temporary trunnion girder. Once the pins were removed, the existing temporary trunnion girder was removed from the downstream side of Pier 2. This cleared the area for core drilling of 8-each 3-inch-diameter holes into Pier 2. These holes will then have eight 1.75-inch-diameter threaded bars installed for the anchorage of the new trunnion girder. Gate 3 repair work started following the installation of the new trunnion girder.

Massman removed the riprap from the downstream side of Gate 2 and Gate 3 to provide a clean surface for the installation of the shoring. 

Previous
Previous

CHALMETTE LEVEE LOOP - BAYOU BIENVENUE TO BAYOU DUPRE, REACH LPV-145

Next
Next

BAYOU PETIT CAILLOU BARGE GATE